Federal grant · formula grant (a)
Application Purpose: the Purpose of This Grant Is to Fund the Land Acquisition Furniture and Construction of Valley Metro Regional Transit Terminal and Maintenance Facility Using $3565185 of FY2020 5307 Federal Funds. Local Match of $713037 Will Come From TDCS Approved by the Texas Department of Transportation on March 10 2023 (approval Attached). the City of Mcallen and Lrgvdc Split the Mcallen Uza Funding. See the Attached Split Letter.in Grant Documents. ; Activities Performed: Construction of the Valley Metro Regional Transit Terminal and Maintenance Facility Will INCLUDE:1. Passenger Waiting and Boarding AREAS2. General Parking Area and Street Side Parking for Passenger Pick-ups and DROP-OFFS3. Ticketing and Information Areas With Way-finding and SIGNAGE.4. Bus Bays and Bus Staging AREAS.5. Retail/commercial Space and Space for LEASE.6. RESTROOMS.7. Security System Cameras Controlled Access Screens and Related EQUIPMENT.8. Valley Metro OFFICES.9. LANDSCAPING.10. LIGHTING.11. Walkways and Walking AREAS.12. Bike Rental and Repair STATION.13. Potential for Car Share Program DEVELOPMENT.14. Maintenance Facility and GARAGE.15. Park and Ride.the Proposed Project and Land Acquisition Will Be Located Near 500 North Milanos RD. in Weslaco Texas and Is Approximately 26.81 Acres (gross Area). the Facility Will Have a Useful Life of 40 Years. the Terminal Will Also House Bicycle Pedestrian Taxis and Other Public Transportation Sources.; Expected Outcomes: This Project Will Improve Mobility in the Area Increase Pedestrian Traffic and Access to Nearby Public Services Encourage Growth of Public Transportation Encourage Economic Development Advance Green Initiatives and Serve as the Main Direct Hub for Lrgvdc Valley Metro.; Intended Beneficiaries: This Project Will Be Valley Metros Main Transportation Hub and Benefit Individuals Throughout the Rio Grande Valley Public Transportation Needs.; Subrecipient Activities: N/a
Committed
$3.6 Million
Paid out
$1.4M
39%
Committed, not yet paid
$2.2M
61%
Loading…
Everything here is this single award's whole record — signed, amended, paid — not a fiscal-year slice. The by-year charts elsewhere split an award across the years it was committed; this page keeps it whole.
Committed is what the government has legally promised on this award so far. Contracts can also carry a ceiling — the maximum if every option is exercised. Unspent ceiling is headroom, not money owed.
The cash actually disbursed against this award. The gap from committed is the disbursement pipeline: promised, not yet cashed.
Each transaction is a signing event — an action that created or changed the award, dated the day it was signed — not a payment. Negative amounts are real: money de-committed at closeout or renegotiation.
One bar, the award’s whole arithmetic: paid out, then committed, not yet paid, then unspent ceiling.