Federal grant · project grant (b)
State Expenditure Plan #10: Bayou La Batre Collection System/lift Station Upgrades --this 42-MONTH Project Includes Planning, Engineering and Design and Construction Required to Rehabilitate the Collection System and Lift Stations in Bayou La Batre, Alabama. Aligned With the Comprehensive Plan Goal to Restore Water Quality, Implementation of This Project Will Result in Fewer Overflows and an Overall Reduction of Contaminants Into Local Soils and Waters. the Collection System Includes 22 Lift Stations Needing Upgrades to the Structures, Pumps, and Controls Along With the Installation of Auxiliary Backup Pumps to Eliminate Sanitary Sewer Overflows Throughout the Collection System. the Upgrades Will Involve Installing Larger Lift Station Pumps With Controls and Installing By-pass Lift Station Pumps Instead of Generators. the Collection System Rehabilitation Is Over Fifteen Miles of Collection System That Is Exhibiting High Infiltration and Inflow. the Collection System Is Recommended to Be Slip Lined, Which the Method Used for Infiltration and Inflow Reduction Less Than Five Years Ago on Other Areas of the Collection System. the Environmental Benefit Is Reduced Infiltration and Inflow and Reduction of Sanitary Sewer Overflows Into Highly Sensitive Waters of the State of Alabama.with a Grant Award of $13,189,150, the Mobile County Commission Will Manage All Design, Permit Compliance and Construction Elements of This Project.
Committed
$15.7 Million
Paid out
$1.1M
7%
Committed, not yet paid
$14.6M
93%
Everything here is this single award's whole record — signed, amended, paid — not a fiscal-year slice. The by-year charts elsewhere split an award across the years it was committed; this page keeps it whole.
Committed is what the government has legally promised on this award so far. Contracts can also carry a ceiling — the maximum if every option is exercised. Unspent ceiling is headroom, not money owed.
The cash actually disbursed against this award. The gap from committed is the disbursement pipeline: promised, not yet cashed.
Each transaction is a signing event — an action that created or changed the award, dated the day it was signed — not a payment. Negative amounts are real: money de-committed at closeout or renegotiation.
One bar, the award’s whole arithmetic: paid out, then committed, not yet paid, then .
Loading…