Federal grant · cooperative agreement (b)
The Goal of This Project Will Be to Establish Manufacturing Processes for Pem Electrolyzers in Rochester, New York Capable of Producing 5GW of Pem Electrolyzer Stacks Per Year, While Achieving the Cost, Production and Performance Targets Described in Table 1 Below and Drawing From Disadvantaged Communities (DACS) to Develop the Skilled Workforce Necessary to Operate the Facility. Based on the Definitions Provided in Foa Appendix D, the Project Will Not Involve the Construction, Alteration And/or Repair of Infrastructure in the United States.
Committed
$42.7 Million
Paid out
$4.7M
11%
Committed, not yet paid
$38.0M
89%
Everything here is this single award's whole record — signed, amended, paid — not a fiscal-year slice. The by-year charts elsewhere split an award across the years it was committed; this page keeps it whole.
Committed is what the government has legally promised on this award so far. Contracts can also carry a ceiling — the maximum if every option is exercised. Unspent ceiling is headroom, not money owed.
The cash actually disbursed against this award. The gap from committed is the disbursement pipeline: promised, not yet cashed.
Each transaction is a signing event — an action that created or changed the award, dated the day it was signed — not a payment. Negative amounts are real: money de-committed at closeout or renegotiation.
One bar, the award’s whole arithmetic: paid out, then committed, not yet paid, then .
Loading…