Increasing Operational Flexibility of Existing Hydropower Through Non-intrusive Feedback Control and Hybridization Ge Research, in Collaboration With Firstlight Power (firstlight), Eagle Creek Renewable Energy (ecre), and Ge Renewable Energy, Represented by Its Hydro Business (geh), Aims to Unlock Previously Untapped Flexibility Within the Existing Hydro Fleet in a Manner That Is Both Cost-effective and Quick-to-implement. the Overall Goal Is to Develop Quick and Affordable Ways to Obtain Additional Sources of Flexibility From Francis-driven Hydropower and PSH Units. the Project Team Will Take Two Approaches to Achieve Their Goals. First, the Project Team Will Assess the Real and Potential Behavior of Installed Equipment and Their Critical Components, Using Feedback From This Assessment to Modify Operational Parameters and Strategies. Second, the Team Will Attempt to Increase Hydropower Operating Ranges Through Implementation of Battery Controls.
Committed
$3.0 Million
Paid out
$885.9K
30%
Committed, not yet paid
$2.1M
70%
Everything here is this single award's whole record — signed, amended, paid — not a fiscal-year slice. The by-year charts elsewhere split an award across the years it was committed; this page keeps it whole.
Committed is what the government has legally promised on this award so far. Contracts can also carry a ceiling — the maximum if every option is exercised. Unspent ceiling is headroom, not money owed.
The cash actually disbursed against this award. The gap from committed is the disbursement pipeline: promised, not yet cashed.
Each transaction is a signing event — an action that created or changed the award, dated the day it was signed — not a payment. Negative amounts are real: money de-committed at closeout or renegotiation.
One bar, the award’s whole arithmetic: paid out, then committed, not yet paid, then .