Federal grant · project grant (b)
The Project Will Bring the Existing Catenary System Assets Into a State of Good Repair With the Replacement of Approximately 215 Ocs Structures From Approximately MP 8.5 to Approximately MP 16.6. the Hell Gate Line Is Used by Amtraks Nec Services and Freight, and the Project Will Increase Reliability and Resilience of the Electrical Traction System for the Current Intercity Passenger Rail Services. Replacing the Catenary Structures Will Also Reduce Risks of Future Structural Failures That Would Cause Passenger Delays.
Committed
$30.0 Million
Paid out
$12.7M
42%
Committed, not yet paid
$17.3M
58%
Everything here is this single award's whole record — signed, amended, paid — not a fiscal-year slice. The by-year charts elsewhere split an award across the years it was committed; this page keeps it whole.
Committed is what the government has legally promised on this award so far. Contracts can also carry a ceiling — the maximum if every option is exercised. Unspent ceiling is headroom, not money owed.
The cash actually disbursed against this award. The gap from committed is the disbursement pipeline: promised, not yet cashed.
Each transaction is a signing event — an action that created or changed the award, dated the day it was signed — not a payment. Negative amounts are real: money de-committed at closeout or renegotiation.
One bar, the award’s whole arithmetic: paid out, then committed, not yet paid, then .
Loading…