Federal grant · formula grant (a)
Project Title: I-10; La 415 to Essen on I-10 and I-12 :::: Project Description: Revised Scope Per 1/12/2021 From A.murrell: Interstate 10 (I-10) Will Be Improved Through Widening and Reconstruction of the Mainline From 3 to 4 Lanes in Each Direction, Including Bridge Replacement and Rehabilitation, Interchange and Ramp Modification, Shoulder Widening, and Auxiliary Lane(s) From La 415 to Essen Lane on I-10 and I-12. the Project Corridor Includes Two Phases. Phase I Includes the Limits of W. of Washington ST. to Essen Lane on I-10 and I-12, and Phase Ii Includes the Limits of La 415 to W. of Washington ST.
Committed
$149.4 Million
Paid out
$120.6M
81%
Committed, not yet paid
$28.8M
19%
Everything here is this single award's whole record — signed, amended, paid — not a fiscal-year slice. The by-year charts elsewhere split an award across the years it was committed; this page keeps it whole.
Committed is what the government has legally promised on this award so far. Contracts can also carry a ceiling — the maximum if every option is exercised. Unspent ceiling is headroom, not money owed.
The cash actually disbursed against this award. The gap from committed is the disbursement pipeline: promised, not yet cashed.
Each transaction is a signing event — an action that created or changed the award, dated the day it was signed — not a payment. Negative amounts are real: money de-committed at closeout or renegotiation.
One bar, the award’s whole arithmetic: paid out, then committed, not yet paid, then .
Loading…